Operations

Location and project details

Where the expansion will be built, what it adds to the site, and how the work is sequenced.

Location

Cameron Parish, Louisiana

The expansion is sited alongside Phase 1 on the west bank of the Calcasieu Ship Channel near Cameron, Louisiana, with direct deep-water access to the Gulf and proximity to existing pipeline infrastructure.

  • Parish: Cameron Parish, Louisiana
  • Waterway: Calcasieu Ship Channel
  • Site coordinates: TBD (confirm with the Project team)
  • Nearest communities: Cameron, Hackberry, Lake Charles
  • Site access: TBD (primary construction route and park-and-ride staging)

Map centered on the Cameron, Louisiana area for orientation. The marker is not a surveyed site location; see the site plan and location maps below.

Aerial view of the project site on the Calcasieu Ship Channel with the Base Project, Expansion Project, Marine Facility, and Shoreline Protection areas outlined (opens the full-size image in a new tab)
Conceptual site plan: Phase 1 (labeled Base Project on the plan), Expansion Project, Marine Facility, and Shoreline Protection along the Calcasieu Ship Channel. Conceptual layout, not to scale.
Map of the Cameron, Louisiana coast with a star marking the project location at the Calcasieu Pass, east of Holly Beach on Highway 82 (opens the full-size image in a new tab)
Project location on the Cameron Parish coast at the Calcasieu Pass, between Holly Beach and Cameron on LA 82.
Regional map of southwest Louisiana and southeast Texas with a star marking the project location near Cameron (opens the full-size image in a new tab)
Regional context: southwest Louisiana Gulf Coast from the Texas state line to Grand Chenier, with LA 27 and LA 82 access routes.

Scope

What the expansion adds

Side-by-side view of Phase 1 and the expansion scope. Expansion capacity is shown as a site total; expansion values are upper bounds and subject to change as pre-FEED sets the design.

ElementPhase 1Expansion
Liquefaction capacity (Mtpa)9.5Sized for a total site capacity of up to 19, Phase 1 plus expansion
Liquefaction trains6Up to 5 new trains
LNG storage250,000 m3Up to 220,000 m3
Marine berths1No additional berths
Feed gas supply1.5 TBtu/d1.5 TBtu/d
Power islandUp to 120 MWUp to 120 MW

Schedule

Key milestones

Indicative sequence. Dates are targets and forward-looking, and will be updated as the project advances through regulatory review.

  1. FERC pre-filing
  2. Final investment decision
  3. Target FERC authorization and notice to proceed
  4. Construction start
  5. Target to enter service

Safety and environment

Designed for safe operations

Process safety, personnel safety, and environmental protection are built into the design basis, from siting and layout through construction execution and operating procedures. Regulatory commitments and community-facing requirements are summarized on the Community page.

Construction traffic

Managing local impacts

Construction logistics, including the park-and-ride program developed with the Cameron Parish Police Jury, are designed to keep heavy traffic off residential roads and improve safety for residents. Details are on the Community page.